Question
|
Can you confirm the due date please, addendum 1 shows both December 29 and December 22.
|
Answer
|
Close date for this BID will be December 29th at 2:00 p.m.
|
Submitted
|
12/12/2022 03:33:44 PM (CT)
|
|
|
Question
|
Since this is a one-time purchase how long do you want pricing held 30 day or 60 days ?
|
Answer
|
Please hold for 60 days.
|
Submitted
|
12/12/2022 09:39:38 AM (CT)
|
|
|
Question
|
Are alternatives being accepted?
|
Answer
|
# 5 on the Attributes
If you are bidding alternate items please add the specifications to the attachment tab.
|
Submitted
|
12/9/2022 08:26:41 AM (CT)
|
|
|
Question
|
Is this awarded by line or by group ?
|
Answer
|
This will be awarded by the package.
|
Submitted
|
12/8/2022 11:13:54 AM (CT)
|
|
|
Question
|
What is the term of of the contract or is this a one time purchase ? How long did you want pricing held ?
|
Answer
|
This specific RFB will be a one time purchase for these campuses.
|
Submitted
|
12/8/2022 09:39:57 AM (CT)
|
|
|
Question
|
Would it acceptable to provide freight charges and installation charges in a separate area other than the product cost line? If so what is that area that we can include this information?
|
Answer
|
The shipping and installation need to be included in the cost of each package.
|
Submitted
|
12/5/2022 11:35:14 AM (CT)
|
|
|