Plano Independent School District is requesting Proposals for Construction Manager at Risk One Step Process for Pearson ECS Kitchen/Dining Addition & Renovation.
Provide a Kitchen/Dining room renovation and addition. All new kitchen equipment. All new building HVAC controls. Upgrade marquee to digital. Provide appropriate signage directing visitors to visitor parking. Replace valves at sprinkler system. Replace Playground fall protection. Any new window glazing provided as part of the addition will require entry resistant film up to 7’. Add access control key cards at exterior doors from classrooms to playgrounds.
The estimated construction budget is $5,220,997
Location – 4000 Eagle Pass
, Plano, TX 75023
RECOMMENDATION TO BOARD OF CM@R APPROVAL: December 12, 2023
Proposed Construction Schedule:
ESTIMATED DESIGN & DOCUMENTATION PHASE: Thru April 19, 2024
ESTIMATED BIDDING & PERMIT: April 22,2024 THRU June 14, 2024
ESTIMATED CONSTRUCTION TIMELINE: June 17, 2024 THRU August, 29, 2025
VIRTUAL OPENING ZOOM CREDENTIALS:
Veronica Couzynse is inviting you to a scheduled Zoom meeting.