Mechanical and Electrical Building Systems, to include minor Structural and Roofing work, related to the replacement of existing air-cooled chillers, gas fired boilers, all chilled and heating water pumps, seven (7) chilled and heating water air handling units, associated roof mounted equipment, piping and ductwork, accessories and power supply revisions. One (1) gas fired roof top unit and new curb will be replaced in the Gymnasium. The existing automatic wet alarm valve assemblies at the fire riser header will be replaced. All existing HVAC controls will be replaced throughout the facility.
The estimated budget and Location:
Estimated Budget-
$1,717,000 and $150,000 owner's contingency
Project Location -
Harrington Elementary School
1540 Baffin Bay Dr, Plano TX 75075
*********************************************************************************
VIRTUAL
OPENING ON December 7, 2023 AT 2:00 pm
Veronica Couzynse is inviting you to a scheduled Zoom meeting.
Topic: Veronica Couzynse's Zoom Meeting - VIRTUAL Opening Harrington ES HVAC Upgrades
Time: Dec 7, 2023 02:00 PM Central Time (US and Canada)
Join Zoom Meeting
https://us05web.zoom.us/j/3804467644?pwd=S09iMHgvR1NyNkx2S2ZqTnYzek5wQT09&omn=84176412659
Meeting ID: 380 446 7644
Passcode: 9S5Att
****************************************************************************
ONSITE Pre-Bid Meeting on November 28, 2023 at 9:00 AM
Please Pre-register at:
https://forms.office.com/r/wjunUv1XjH