Question
|
If you are matching old tables, that would make sense. There was nowhere on the bid that this was a sole source approved by the state, and there was also nowhere for equal data to be submitted to get approved. We would like to confirm that this is an approved bid and that it follows all of the states requirements. To be brand-specific, it needs to have special approval. Please confirm.
|
Answer
|
Brand and items specified in the RFP are preferred. This is not a sole source solicitation. Thank you for your input.
|
Submitted
|
11/16/2023 05:45:16 PM (CT)
|
|
|
Question
|
Good Morning,
We are the distributor for all school furniture lines. We noticed on the bid it did not say Brand Specific but did give exact specs. If you are purchasing new tables or each of the two-schools listed is it fair to say as long as the tables we are supplying meet quality standards , are certified and meet exact specifications we are able to submit a bid?
|
Answer
|
We are wanting Rush-Classroom Select and McWhorter -Palmer Hamilton
|
Submitted
|
11/16/2023 10:06:14 AM (CT)
|
|
|
Question
|
Do the tables for Rush Elementary have a brand or a SKU, or are you open to brand substitutions?
|
Answer
|
The tables at Rush specified are Classroom Select
|
Submitted
|
11/14/2023 08:24:27 AM (CT)
|
|
|
Question
|
Are there cafeteria tables already in place that will need to be removed by our installation team?
|
Answer
|
We will schedule those to be removed before the new tables arrive.
|
Submitted
|
11/14/2023 08:17:19 AM (CT)
|
|
|
Question
|
Is there a loading dock at either school, or will a lift gate be needed?
|
Answer
|
A liftgate will be needed.
|
Submitted
|
11/14/2023 08:16:46 AM (CT)
|
|
|
Question
|
Are we allowed to submit a partial bid?
|
Answer
|
Yes
|
Submitted
|
11/9/2023 05:43:55 AM (CT)
|
|
|
Question
|
Once awarded will the orders be placed before the end of 2023? Manufacturers are looking at a price increases at the first of the year and can only guarantee pricing through 12-31-23.
|
Answer
|
Yes, we hope to have PO's entered before end of year. If this needs to be board approved that meeting is set for December 14th.
|
Submitted
|
11/8/2023 10:55:26 AM (CT)
|
|
|
Question
|
Are Substitutes allowed?
|
Answer
|
Substitutes are not preferred, but are allowed.
|
Submitted
|
11/7/2023 12:19:16 PM (CT)
|
|
|
Question
|
When will delivery/purchase take place?
|
Answer
|
Once we close this BID and review prices we will award.
|
Submitted
|
11/7/2023 12:18:53 PM (CT)
|
|
|
Question
|
What is the determining factor for award?
|
Answer
|
Price
|
Submitted
|
11/7/2023 12:18:42 PM (CT)
|
|
|