Question
|
Could you please add/Substitute Dur-A-Flex as an approved manufacturer for resinous flooring due to the exclusivity of Stonhard?
SYSTEM OVERVIEW
Manufacturer-DUR-A-FLEX-Product-HYBRI-FLEX EQ is a seamless, nominal 3/16" – 1/4" decorative quartz floor system featuring a moisture-tolerant self-priming and self-leveling body coat topped with a double broadcast of decorative quartz aggregate and finished with an Armor Top topcoat for a chemical, UV, and wear-resistant urethane topcoat.
|
Answer
|
Via Addendum 2
|
Submitted
|
5/24/2023 12:07:31 PM (CT)
|
Asked By
|
Summit Building & Design
|
|
|
Question
|
As per Elevation 8/A3.01, CWT-4 & CWT-9 Wall Tile Indicated with indication of RE:9/A3.02. However, Room Finish Schedule Indicated CWT-6 & CWT-9 Wall Tile
Therefore, CWT-6 & CWT-9 Wall Tile Estimated with RE:10/A3.02 at Vanity Wall.
Also CWT-1 Wall Tile Indicated at Other Walls, Refer Elevations 9,10,11/A3.01
|
Answer
|
Via Addendum 2
|
Submitted
|
5/24/2023 11:12:05 AM (CT)
|
Asked By
|
Summit Building & Design
|
|
|
Question
|
On Sheet A3.02, 9,10,11/A3.02, Mosaic Pattern of Different Wall Tile Indicated. However, No Percentage or Height or Hatch Provided. For Now, These Pattern Have been Estimated by Taking Heights of each Tile.
|
Answer
|
Via Addendum 2
|
Submitted
|
5/24/2023 11:11:40 AM (CT)
|
Asked By
|
Summit Building & Design
|
|
|
Question
|
As per Elevation 04/A9.03, CWT-6 & CWT-9 Wall Tile Indicated on Countertop with reference to 10/A3.02. However, Elevation 10/A3.02 Indicates CWT-5, CWT-6, CWT-9, CWT-8, CWT-7 Wall Tile at 23’11” Height which does not match the height of countertop. For Now, CWT-6 & CWT-9 Combine Layer Estimated.
Please clarify.
|
Answer
|
Via Addendum 2
|
Submitted
|
5/24/2023 11:11:07 AM (CT)
|
Asked By
|
Summit Building & Design
|
|
|
Question
|
Per Addendum #1-Is the guard shack a pre-manufactured building or will there need to be lighting and a power field installed?
|
Answer
|
Via Addendum 2
|
Submitted
|
5/24/2023 10:46:47 AM (CT)
|
Asked By
|
Summit Building & Design
|
|
|
Question
|
Per Addendum #1 Site plan “Mep1-02 Mep Site Plan - Addn 1_74” does not show the electrical feed for the guard shack panel but the one line does, this is still required?
|
Answer
|
Via Addendum 2
|
Submitted
|
5/24/2023 10:45:49 AM (CT)
|
Asked By
|
Summit Building & Design
|
|
|
Question
|
Will you replace the Proposal invitation cover page with the new bid date?
|
Answer
|
no
|
Submitted
|
5/23/2023 05:20:20 PM (CT)
|
|
|
Question
|
Addendum # 1 extends the bid date. Will the date to submit the final question be extended also?
|
Answer
|
no
|
Submitted
|
5/23/2023 05:17:49 PM (CT)
|
|
|
Question
|
Bid Schedule – show Base Bid broken down into 7 items. Where would do you want us to place the cost for General Requirements, Insurances, Builder Risk, & Bond? Will you consider separate line items for this?
|
Answer
|
Via Addendum 2
|
Submitted
|
5/23/2023 05:17:09 PM (CT)
|
Asked By
|
Summit Building & Design
|
|
|
Question
|
Sht A10.02- Second Floor RCP – Showing shaded- Suspended Gypsum Board in the Exterior Dock Area. Section A7.04 show Tremco Tremlock on Hat Channels. Please Clarify.
|
Answer
|
Via Addendum 2
|
Submitted
|
5/23/2023 05:16:50 PM (CT)
|
Asked By
|
Summit Building & Design
|
|
|